JES-3 & JES-4

The GREENECO GPP-3 power plant, which consists of 2 units in total, has an installed capacity of 25.6 Megawatts.

 

UNIT 1 (12.8 MWe)

PLANT START: 15.01.2017

PLANT END: 01.10.2017

MINISTRY'S ACCEPTANCE: 13.10.2017

TRANSITION TO BUSINESS: 14.10.2017

 

 

UNIT 2 (12.8 MWe)

PLANT START: 05.12.2017

PLANT END: 26.09.2018

MINISTRY'S ACCEPTANCE: 30.09.2018

TRANSITION TO BUSINESS: 01.10.2018

 

The installed power of 25.6 MWe has an annual electricity generation capacity of 204,800,000 kWh.

It contributes to the reduction of the current account deficit of our country by preventing imports of approximately 22 million dollars each year for approximately 50 million m3 of natural gas annually.