GREENECO JES-6 POWER PLANT
The installed power of 106mw has been reached.
Consisting of 1 unit, the GREENECO JES-6 power plant has reached an installed capacity of 106 MW.
UNIT 1 (26.0 MWe)
PLANT START: 05.11.2019
PLANT END: 30.09.2020
MINISTRY'S ACCEPTANCE: 09.10.2020
TRANSITION TO BUSINESS: 09.10.2020
The installed power of 106 mw will have an annual electricity generation capacity of 191,360,000 kWh.
It will contribute to the reduction of the current account deficit of our country by preventing imports of approximately 20 million dollars each year for approximately 45 million m3 of natural gas annually.